Well, rain again earlier this week!
The Crew has been really busy working out the details on the ridge vents. The original plans detailed the design, but left certain dimensions to the discretion of the local area.
The roofing system award went to a local contractor, CR Systems. They will begin work on the 15th. Getting ready for them means the exterior siding needs to go up, the soffits and facsia in place, the plumber needs to have the drain vents through the roof and, if possible, the painter needs to have the exterior painted. Hopefully, it will all fall into place.